Resolution#220791Passed
In plain English

This resolution allows the General Manager of the San Francisco Public Utilities Commission to extend and increase funding for a contract related to the Southeast Plant Biosolids Digester Facilities by $55 million, bringing the total to $208.5 million. It also extends the contract duration by three and a half years, now lasting until July 28, 2029.

Resolution authorizing the General Manager of the San Francisco Public Utilities Commission to execute Amendment No. 2 to Wastewater Enterprise Contract No. CS-235, Planning and Engineering Services, Southeast Plant (SEP) Biosolids Digester Facilities, with Brown and Caldwell, to increase the contract amount by $55,000,000 for a total not to exceed amount of $208,500,000 and increase the contract duration by three years and six months, for a total duration of 16 years from July 29, 2013, through July 28, 2029, pursuant to Charter, Section 9.118.

Introduced: Jul 12, 2022
Final action: Oct 6, 2022
Official record ↗

How it got here

Related / predecessor legislation
↑ predecessor#130589— not yet in database
↑ predecessor#170344— not yet in database
Document trail
PDF ↗
PDF ↗
PDF ↗
PDF ↗
PDF ↗
PDF ↗
PDF ↗
PDF ↗
PDF ↗
PDF ↗
PDF ↗
BLA Rpt 092122
Budget and Legislative Analyst
PDF ↗
PDF ↗
PDF ↗
PDF ↗
PDF ↗
PDF ↗

How they voted

AMENDED, AN AMENDMENT OF THE WHOLE BEARING SAME TITLE
Budget and Finance Committee · Sep 21, 2022Pass
1-0
RECOMMENDED AS AMENDED
Budget and Finance Committee · Sep 21, 2022Pass
1-0

Legislative journey

Clerk of the BoardJul 1, 2022
·RECEIVED FROM DEPARTMENT
PresidentJul 12, 2022
RECEIVED AND ASSIGNED
Budget and Finance CommitteeSep 21, 2022
RECOMMENDED AS AMENDEDPass
AMENDED, AN AMENDMENT OF THE WHOLE BEARING SAME TITLEPass
Board of SupervisorsSep 27, 2022
ADOPTEDPass
MayorOct 6, 2022
APPROVED
Public Utilities CommissionJan 9, 2024
·RESPONSE RECEIVED