The ordinance allows the San Francisco Public Utilities Commission and the City Attorney to settle claims related to the September 10, 2023, water pipeline break for amounts over $25,000, up to a maximum of $1,000,000 per claim, with a total cap of $7,000,000 for all claims. It also requires periodic reporting to the Board of Supervisors' Government Audit and Oversight Committee.

Ordinance authorizing the San Francisco Public Utilities Commission (SFPUC) and the Office of the City Attorney to approve settlements of claims arising out of the September 10, 2023, break of the SFPUC's water transmission pipeline at the intersection of Fillmore and Green Streets for amounts exceeding $25,000 per claim, notwithstanding Administrative Code, Section 10.22, et. seq., but not to exceed $1,000,000 per claim, and delegating authority under Charter, Section 6.102(5) for the settlement of related litigation, if any, up to an aggregate total settlement amount not to exceed $7,000,000, subject to periodic reporting to the Board of Supervisors Government Audit and Oversight Committee.

Introduced: Dec 12, 2023
Final action: Feb 9, 2024
Official record โ†—

How it got here

Document trail
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—

How they voted

FINALLY PASSED
Board of Supervisors ยท Jan 30, 2024Pass
5-0
PASSED ON FIRST READING
Board of Supervisors ยท Jan 23, 2024Pass
5-0
RECOMMENDED AS COMMITTEE REPORT
Government Audit and Oversight Committee ยท Jan 18, 2024Pass
0-0 /1

Legislative journey

PresidentDec 12, 2023
โ†’ASSIGNED UNDER 30 DAY RULE
Clerk of the BoardDec 15, 2023
โ†’REFERRED TO DEPARTMENT
Government Audit and Oversight CommitteeJan 18, 2024
โœ“RECOMMENDED AS COMMITTEE REPORTPass
Board of SupervisorsJan 23, 2024 โ€“ Jan 30, 2024
โœ“PASSED ON FIRST READINGPass
โœ“FINALLY PASSEDPass
MayorFeb 9, 2024
โœ“APPROVED