Resolution#240625Passed
In plain English

This resolution allows the San Francisco Public Utilities Commission to increase funding and extend the contract with HDR Engineering Inc. for construction management services related to the Southeast Water Pollution Control Plant project. The total contract amount will rise to $31,680,626 and the duration will be extended to December 14, 2025.

Resolution authorizing the General Manager of the San Francisco Public Utilities Commission to execute Amendment No. 3 to the New Headworks Facility Construction Management Staff Augmentation Services Agreement PRO.0028 with HDR Engineering Inc.; increasing the agreement by $4,680,626 for a total not to exceed amount of $31,680,626 and extending the duration by one year, for a total term of eight years and six months of June 15, 2017, through December 14, 2025, to reflect the re-scoping efforts and increased level of staffing needed to complete the construction of the Southeast Water Pollution Control Plant New Headworks Facility, pursuant to Charter, Section 9.118.

Introduced: Jun 11, 2024
Final action: Jul 26, 2024
Official record โ†—

How it got here

The legislation originated from the need to amend a contract for construction management services related to the Southeast Water Pollution Control Plant's New Headworks Facility.

1
Initial Contract AwardMarch 28, 2017
San Francisco Public Utilities Commission (SFPUC)

The SFPUC awarded Agreement No. PRO.0028 to HDR Engineering, Inc. for construction management staff augmentation services, with a total not to exceed amount of $17,000,000 and a duration of six years.

SFPUC Resolution No. 17-0059
2
Approval of Initial ContractMay 16, 2017
Board of Supervisors

The Board of Supervisors authorized the General Manager of the SFPUC to execute the contract with HDR Engineering, Inc.

Board Resolution No. 191-17
3
First Amendment to ContractJuly 14, 2020
SFPUC

The SFPUC approved Amendment No. 1 to increase the contract amount by $10,000,000, raising the total to $27,000,000, and extending the duration by one year.

SFPUC Resolution No. 20-0152
4
Second Amendment to ContractMay 7, 2024
SFPUC

The SFPUC executed Amendment No. 2, extending the contract duration by six months without changing the agreement amount.

SFPUC Resolution No. 09-0017
5
Third Amendment AuthorizationMay 28, 2024
SFPUC

The SFPUC authorized Amendment No. 3 to increase the contract by $4,680,626, bringing the total to $31,680,626, and extending the duration by one year.

SFPUC Resolution No. 24-0123
6
Committee RecommendationJuly 10, 2024
Budget and Finance Committee

The Budget and Finance Committee recommended the approval of the resolution for Amendment No. 3.

Committee Packet
7
Final ApprovalJuly 16, 2024
Board of Supervisors

The Board of Supervisors adopted the resolution authorizing the General Manager of the SFPUC to execute Amendment No. 3.

Leg Final

Reconstructed from attached documents & the official record

Document trail
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
BLA Rpt 071024
Budget and Legislative Analyst
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—

How they voted

RECOMMENDED
Budget and Finance Committee ยท Jul 10, 2024Pass
3-0

Legislative journey

Clerk of the BoardMay 31, 2024
ยทRECEIVED FROM DEPARTMENT
PresidentJun 11, 2024
โ†’RECEIVED AND ASSIGNED
Budget and Finance CommitteeJul 10, 2024
โœ“RECOMMENDEDPass
Board of SupervisorsJul 16, 2024
โœ“ADOPTEDPass
MayorJul 26, 2024
โœ“APPROVED