Resolution#240954Passed
In plain English

This resolution allows the San Francisco Public Utilities Commission to hire Consor PMCM, Inc. for construction management services related to the new City Distribution Division Campus at 2000 Marin, with a budget of up to $10,720,500 over a period of four years and three months. The contract will run from February 2025 to April 2029.

Resolution approving and authorizing the General Manager of the San Francisco Public Utilities Commission (SFPUC) to execute Professional Services Agreement, Contract No. PRO.0239, New City Distribution Division Campus at 2000 Marin Construction Management Staff Augmentation Services, with Consor PMCM, Inc., to supplement the SFPUCโ€™s Construction Management Bureau staff in overseeing the construction of the new City Distribution Division Campus at 2000 Marin project, for an amount not to exceed $10,720,500 and with a term duration of four years and three months, from February 2025, through April 2029, pursuant to Charter, Section 9.118.

Introduced: Oct 8, 2024
Final action: Nov 14, 2024
Official record โ†—

How it got here

The legislation originated from the need to address overcrowding and operational inefficiencies at the San Francisco Public Utilities Commission's City Distribution Division, prompting the construction of a new campus.

1
Construction Contract AwardedJune 28, 2022
San Francisco Public Utilities Commission

The SFPUC awarded Contract No. WD-2897R to Clark Construction Group for construction services for the New City Distribution Division Campus at 2000 Marin Street.

SFPUC Reso No. 24-0176
2
Preliminary Mitigated Negative Declaration PublishedJune 19, 2024
San Francisco Planning Department

The Planning Department published a Preliminary Mitigated Negative Declaration for the project, which was available for public comment until July 19, 2024.

SFPUC Reso No. 24-0176
3
Final Mitigated Negative Declaration ApprovedJuly 29, 2024
San Francisco Planning Department

The Planning Department approved the Final Mitigated Negative Declaration for the project, confirming it would not have a significant effect on the environment.

SFPUC Reso No. 24-0209
4
Project Approval and Findings AdoptedAugust 13, 2024
San Francisco Public Utilities Commission

The SFPUC adopted the Final Mitigated Negative Declaration and approved the project, including findings required under CEQA.

SFPUC Reso No. 24-0176
5
Professional Services Agreement ApprovedSeptember 24, 2024
San Francisco Public Utilities Commission

The SFPUC approved the Professional Services Agreement with Consor PMCM, Inc. for construction management services, with a total cost not to exceed $10,720,500.

SFPUC Reso No. 24-0209
6
Legislation AdoptedNovember 5, 2024
San Francisco Board of Supervisors

The Board of Supervisors adopted the resolution authorizing the General Manager of the SFPUC to execute the Professional Services Agreement with Consor PMCM, Inc.

Leg Final

Reconstructed from attached documents & the official record

Document trail
PDF โ†—
PDF โ†—
PDF โ†—
PLN Mit Neg Dec 061924
SF Planning Department
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
BLA Rpt 103024
Budget and Legislative Analyst
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—

How they voted

RECOMMENDED
Budget and Finance Committee ยท Oct 30, 2024Pass
3-0

Legislative journey

Clerk of the BoardSep 27, 2024
ยทRECEIVED FROM DEPARTMENT
PresidentOct 8, 2024
โ†’RECEIVED AND ASSIGNED
Budget and Finance CommitteeOct 30, 2024
โœ“RECOMMENDEDPass
Board of SupervisorsNov 5, 2024
โœ“ADOPTEDPass
MayorNov 14, 2024
โœ“APPROVED
Clerk of the BoardDec 12, 2024