Resolution#241058Passed
In plain English

This resolution approves an increase of $9.5 million to a contract with AECOM Technical Services for construction management services related to the Mountain Tunnel Improvements Project, raising the total contract amount to $34 million. It also extends the contract duration by five months, now set to end on December 30, 2027.

Resolution approving and authorizing the General Manager of the San Francisco Public Utilities Commission to execute Amendment No. 3 to Professional Services Agreement No. PRO.0096, Mountain Tunnel Improvement Construction Management Services, with AECOM Technical Services, Inc., increasing the contract by $9,500,000 for a total contract not to exceed amount of $34,000,000 and extending the contract duration by five months from July 31, 2027, for a total contract term from July 31, 2019, through December 30, 2027, to continue providing specialized construction management services for the Mountain Tunnel Improvements Project, pursuant to Charter, Section 9.118.

Introduced: Nov 5, 2024
Final action: Jan 31, 2025
Official record โ†—

How it got here

The legislation originated from the need for continued construction management services for the Mountain Tunnel Improvements Project, following prior approvals and amendments to the contract with AECOM Technical Services, Inc.

1
Request for Proposals IssuedOctober 10, 2018
San Francisco Public Utilities Commission (SFPUC)

The SFPUC advertised a Request for Proposals for construction management services for the Mountain Tunnel Improvements Project.

Leg Final
2
Contract AwardedApril 23, 2019
SFPUC

The SFPUC awarded Contract No. PRO.0096 to AECOM Technical Services, Inc. for a not-to-exceed amount of $24,500,000 and a duration of eight years.

SFPUC Reso No. 19-0085
3
Contract AuthorizedJune 5, 2019
Board of Supervisors

The Board authorized the General Manager of the SFPUC to enter into the professional services agreement with AECOM.

Leg Final
4
First Amendment ExecutedJanuary 4, 2021
SFPUC

Amendment No. 1 was executed to include Community Benefits language that was inadvertently omitted from the original agreement.

Leg Final
5
Second Amendment ExecutedAugust 6, 2021
SFPUC

Amendment No. 2 was executed to correct an error in the Other Direct Costs language without changing the contract amount or duration.

Leg Final
6
Third Amendment ApprovedOctober 22, 2024
SFPUC

The SFPUC approved Amendment No. 3 to increase the contract amount by $9,500,000 and extend the contract duration by five months.

SFPUC Reso No. 24-0221
7
Resolution AdoptedJanuary 28, 2025
Board of Supervisors

The Board of Supervisors adopted the resolution approving Amendment No. 3, bringing the total contract amount to $34,000,000.

Leg Final

Reconstructed from attached documents & the official record

Related / predecessor legislation
โ†‘ predecessor#190486โ€” not yet in database
Document trail
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
BLA Rpt 012225
Budget and Legislative Analyst
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—

How they voted

Legislative journey

Clerk of the BoardOct 25, 2024
ยทRECEIVED FROM DEPARTMENT
PresidentNov 5, 2024
โ†’RECEIVED AND ASSIGNED
Budget and Finance CommitteeJan 22, 2025
โœ“RECOMMENDEDPass
Board of SupervisorsJan 28, 2025
โœ“ADOPTEDPass
MayorJan 31, 2025
โœ“APPROVED