Resolution#241136Passed
In plain English

This resolution endorses a financial agreement for the modernization of the Potrero Yard by the San Francisco Municipal Transportation Agency, outlining specific milestone payments and terms for the project. It includes provisions for payments totaling up to $75 million initially, with additional payments and adjustments over a 30-year maintenance term, pending final approval by the Board of Supervisors.

Resolution generally endorsing the form of an Infrastructure Facility Design-Build-Finance-Operate-Maintain Agreement (Form Project Agreement) for the San Francisco Municipal Transportation Agency (SFMTA) Potrero Yard Modernization Project, and the following pricing: 1) an initial milestone payment of up to $75,000,000 at financial close, 2) a relocation payment of up to $500,000 within 60 days of completing temporary relocation of Potrero Yard operations, 3) a milestone payment of up to $200,000,000 by no later than 2033, and 4) an initial maximum annual availability payment of up to $42,200,000 (in Fiscal Year 2030 dollars) over a maintenance term not to exceed 30 years after the scheduled substantial completion date, anticipated in 2029, subject to interest rate and credit spread fluctuations between commercial close and financial close and annual Consumer Price Index adjustments, with the part of the payment covering capital costs increasing 1% per year and sculpted to align with the SFMTA’s existing debt service obligations; and providing that the final terms of the agreement, including final pricing and inclusion of a Small Business Enterprise/Disadvantaged Business Enterprise Plan, shall be subject to approval of the Board of Supervisors.

Introduced: Nov 19, 2024
Final action: Dec 19, 2024
Official record β†—

How it got here

The Potrero Yard Modernization Project originated from the need to replace an outdated transit facility and integrate affordable housing, driven by city policies promoting joint development.

1
Authorization for Joint Development ProcurementApril 7, 2020
SFMTA Board of Directors

The SFMTA Board authorized the use of a joint development procurement method for the Potrero Yard Modernization Project.

Leg Ver1
2
Approval of Joint Development Delivery MethodMarch 16, 2021
Board of Supervisors

The Board approved a joint development delivery method and exempted various project agreements from certain administrative code requirements.

Leg Ver1
3
Execution of Predevelopment AgreementNovember 1, 2022
SFMTA Board of Directors

The SFMTA Board authorized the Director of Transportation to execute a Predevelopment Agreement with Potrero Neighborhood Collective LLC, the selected developer.

MTA Reso No. 221101-105
4
Predevelopment Agreement ExecutedNovember 2, 2022
SFMTA and Potrero Neighborhood Collective LLC

The Predevelopment Agreement was fully executed, marking the start of predevelopment activities for the project.

Executed Predev Agrmt 110222
5
Certification of Final Environmental Impact ReportJanuary 11, 2024
Planning Commission

The Planning Commission certified the Final Environmental Impact Report for the project, completing the environmental review process.

PC Motion No. 21482
6
Approval of Project Agreement TermsDecember 3, 2024
SFMTA Board of Directors

The SFMTA Board approved the terms of the Infrastructure Facility Design-Build-Finance-Operate-Maintain Agreement, subject to final pricing.

MTA Reso No. 241203-140
7
Adoption of ResolutionDecember 10, 2024
Board of Supervisors

The Board of Supervisors adopted the resolution endorsing the Project Agreement for the Potrero Yard Modernization Project.

Leg Final

Reconstructed from attached documents & the official record

Related / predecessor legislation
↑ predecessor#231256β€” not yet in database
↑ predecessor#240047β€” not yet in database
↑ predecessor#240136β€” not yet in database
↑ predecessor#240937β€” not yet in database
↑ predecessor#260185β€” not yet in database
Document trail
PDF β†—
PDF β†—
PDF β†—
PDF β†—
PDF β†—
PDF β†—
SFMTA Briefing Ltr 111924
SF Municipal Transportation Agency
PDF β†—
PDF β†—
PDF β†—
BLA Rpt 120424
Budget and Legislative Analyst
PDF β†—
PDF β†—
MTA Presentation 120424
SF Municipal Transportation Agency
PDF β†—
MTA Reso No. 241203-140 120324
SF Municipal Transportation Agency
PDF β†—
PDF β†—
PDF β†—
PDF β†—

How they voted

AMENDED, AN AMENDMENT OF THE WHOLE BEARING NEW TITLE
Budget and Finance Committee Β· Dec 4, 2024Pass
3-0
RECOMMENDED AS AMENDED
Budget and Finance Committee Β· Dec 4, 2024Pass
3-0

Legislative journey

PresidentNov 19, 2024
β†’RECEIVED AND ASSIGNED
Budget and Finance CommitteeDec 4, 2024
βœ“RECOMMENDED AS AMENDEDPass
✎AMENDED, AN AMENDMENT OF THE WHOLE BEARING NEW TITLEPass
Municipal Transportation AgencyDec 4, 2024
Β·RESPONSE RECEIVED
Board of SupervisorsDec 10, 2024
βœ“ADOPTEDPass
MayorDec 19, 2024
βœ“APPROVED