SF QuorumQuorum
Back to legislation
Resolution#241139Passed
In plain English

This resolution approves a 25-year lease agreement for training facilities on Treasure Island, with a minimum monthly rent of $1 until occupancy, then increasing to $27,750 per month. It also confirms that no new environmental impacts will arise from the lease and allows for minor amendments to the lease terms.

Resolution making California Environmental Quality Act findings and confirming the San Francisco Planning Department’s determination that no additional environmental impacts that were not previously identified would occur as a result of the proposed lease; and approving and authorizing the execution of a 25-year lease agreement after approval of this Resolution with four consecutive five-year extension options, between the Treasure Island Development Authority and BAFC Team Operator, LLC for its training facilities on approximately 8.49 acres of land on Treasure Island, with a minimum monthly base rent of $1 from the commencement of the lease until the occupancy date, and $27,750 per month thereafter; and to authorize the Treasure Island Director to enter into amendments or modifications to the lease and the parking lease terms that do not materially increase the obligations or liabilities to the City and are necessary to effectuate the purposes of the lease or this Resolution.

Introduced: Nov 19, 2024
Final action: Dec 19, 2024
Official record β†—

How it got here

The legislation originated from the need to establish a permanent training facility for the Bay Football Club on Treasure Island, following prior environmental assessments and planning approvals.

1
Certification of Environmental Impact ReportApril 21, 2011
San Francisco Planning Commission

The Planning Commission certified the completion of the 2011 Final Environmental Impact Report (FEIR) for the Treasure Island/Yerba Buena Island Project, which included the site for the future training facility.

PC Motion No. 18325
2
Affirmation of Environmental FindingsJune 7, 2011
San Francisco Board of Supervisors

The Board unanimously affirmed the certification of the 2011 FEIR and adopted CEQA findings and a Mitigation Monitoring and Reporting Program.

Leg Final
3
Letter of Intent SignedAugust 2024
Treasure Island Development Authority (TIDA) and Bay FC

TIDA and Bay FC signed a Letter of Intent to negotiate a lease agreement for a training facility on Treasure Island.

OEWD Presentation 120424
4
Approval of Lease and CEQA FindingsNovember 13, 2024
TIDA Board of Directors

The TIDA Board confirmed that no additional environmental impacts would occur from the proposed lease and approved the lease agreement with Bay FC.

TIDA Reso No. 24-31-1113
5
Adoption of ResolutionDecember 10, 2024
San Francisco Board of Supervisors

The Board adopted the resolution approving the lease agreement with Bay FC for the training facility, which includes a minimum monthly rent structure.

Leg Final

Reconstructed from attached documents & the official record

Related / predecessor legislation
↑ predecessor#110328β€” not yet in database
↑ predecessor#110619β€” not yet in database
Document trail
PDF β†—
PDF β†—
PLN 2024 Memorandum 110824
SF Planning Department
PDF β†—
PDF β†—
PDF β†—
PDF β†—
PDF β†—
PDF β†—
BLA Rpt 120424
Budget and Legislative Analyst
PDF β†—
PDF β†—
PDF β†—
PDF β†—
PDF β†—

How they voted

RECOMMENDED
Budget and Finance Committee Β· Dec 4, 2024Pass
3-0

Legislative journey

PresidentNov 19, 2024
β†’RECEIVED AND ASSIGNED
Budget and Finance CommitteeDec 4, 2024
βœ“RECOMMENDEDPass
Board of SupervisorsDec 10, 2024
βœ“ADOPTEDPass
MayorDec 19, 2024
βœ“APPROVED