A formal position or approval by the Board: Allow the Port of San Francisco to execute Amendment No.
Resolution retroactively authorizing the Port of San Francisco to execute Amendment No. 6 to a professional services contract with COWI/OLMM Joint Venture for architectural and engineering services for the Mission Bay Ferry Landing Project; extending the contract term retroactively from June 16, 2026, for a total term of January 3, 2017, through June 30, 2028, with no changes to the contract amount of $6,411,383.
How it got here
The legislation originated from the need to extend the contract for architectural and engineering services for the Mission Bay Ferry Landing Project due to project delays and additional requirements.
The Port Commission authorized staff to advertise a Request for Proposals for professional architectural and engineering consulting services for the Mission Bay Ferry Landing Project.
The Port Commission awarded a contract to COWI/OLMM Joint Venture for $3,981,369, with a contingency fund, for architectural and engineering services for the Mission Bay Ferry Landing Project.
The Port Commission executed Amendment No. 2 to increase the contract amount by $785,166, resulting in a total not-to-exceed amount of $4,766,535 due to unforeseen conditions requiring additional engineering services.
The Port Commission executed Amendment No. 3 to extend the contract term through January 3, 2024.
The Port Commission executed Amendment No. 4 to extend the contract term through June 16, 2026.
The Port Commission executed Amendment No. 5 to increase the contract amount by $1,644,848, bringing the total to $6,411,383.
The Port Commission adopted Resolution No. 26-02 authorizing execution of Amendment No. 6 to extend the contract term through June 30, 2028.
The resolution for Amendment No. 6 was received from the Port of San Francisco.