This resolution authorizes the San Francisco Public Utilities Commission to amend an existing contract with Jacobs Associates for engineering services related to the Mountain Tunnel Improvements Project, increasing the contract amount by $2 million to a total of $30.78 million. The duration of the contract remains unchanged, running from February 15, 2016, to February 14, 2029.
Resolution approving and authorizing the General Manager of the San Francisco Public Utilities Commission to execute Amendment No. 2 to the Mountain Tunnel Improvements Project, Agreement No. CS-249, Planning and Design Services, Mountain Tunnel Improvements, with Jacobs Associates, Inc., dba Delve Underground, formerly known as McMillen Jacobs Associates, Inc. (Jacobs Associates, Inc., dba Delve Underground), to continue to provide specialized engineering services during construction for the Mountain Tunnel Improvements Project, increasing the contract amount by $2,000,000 for a new total not to exceed contract amount of $30,780,000 with no change to the contract duration of February 15, 2016, through February 14, 2029, pursuant to Charter, Section 9.118.
How it got here
The legislation originated from the need to amend an existing contract for specialized engineering services related to the Mountain Tunnel Improvements Project.
The Board approved the original Agreement No. CS-249 with Jacobs Associates, Inc. for planning and design services for the Mountain Tunnel Improvements, with a contract amount not to exceed $21,000,000.
The SFPUC awarded Agreement No. CS-249 to Jacobs Associates, Inc. for planning and design services related to the Mountain Tunnel Improvements.
The SFPUC approved Amendment No. 1 to increase the contract amount by $7,780,000 and extend the duration to February 14, 2029, to support ongoing construction.
The Board approved Amendment No. 1, increasing the total contract amount to $28,780,000 and extending the duration to 13 years.
The SFPUC approved Amendment No. 2 to increase the contract amount by $2,000,000, bringing the total to $30,780,000, with no change to the contract duration.
The Clerk received the proposed resolution for Amendment No. 2 from the SFPUC.
The resolution for Amendment No. 2 is currently pending committee action.