Resolution#261077Mayors Office
In plain English

This resolution authorizes the San Francisco Public Utilities Commission to amend an existing contract with Jacobs Associates for engineering services related to the Mountain Tunnel Improvements Project, increasing the contract amount by $2 million to a total of $30.78 million. The duration of the contract remains unchanged, running from February 15, 2016, to February 14, 2029.

Resolution approving and authorizing the General Manager of the San Francisco Public Utilities Commission to execute Amendment No. 2 to the Mountain Tunnel Improvements Project, Agreement No. CS-249, Planning and Design Services, Mountain Tunnel Improvements, with Jacobs Associates, Inc., dba Delve Underground, formerly known as McMillen Jacobs Associates, Inc. (Jacobs Associates, Inc., dba Delve Underground), to continue to provide specialized engineering services during construction for the Mountain Tunnel Improvements Project, increasing the contract amount by $2,000,000 for a new total not to exceed contract amount of $30,780,000 with no change to the contract duration of February 15, 2016, through February 14, 2029, pursuant to Charter, Section 9.118.

Introduced: Oct 6, 2026
Final action: Oct 6, 2026
Official record โ†—

How it got here

The legislation originated from the need to amend an existing contract for specialized engineering services related to the Mountain Tunnel Improvements Project.

1
Approval of Original AgreementJune 17, 2015
San Francisco Board of Supervisors

The Board approved the original Agreement No. CS-249 with Jacobs Associates, Inc. for planning and design services for the Mountain Tunnel Improvements, with a contract amount not to exceed $21,000,000.

Exec. Original Agmt 020126
2
Award of AgreementOctober 27, 2015
San Francisco Public Utilities Commission

The SFPUC awarded Agreement No. CS-249 to Jacobs Associates, Inc. for planning and design services related to the Mountain Tunnel Improvements.

PUC Reso No. 26-0150 090826
3
Approval of First AmendmentApril 12, 2022
San Francisco Public Utilities Commission

The SFPUC approved Amendment No. 1 to increase the contract amount by $7,780,000 and extend the duration to February 14, 2029, to support ongoing construction.

PUC Reso No. 26-0150 090826
4
Approval of First Amendment by BoardJune 17, 2022
San Francisco Board of Supervisors

The Board approved Amendment No. 1, increasing the total contract amount to $28,780,000 and extending the duration to 13 years.

Leg Ver1
5
Approval of Second AmendmentSeptember 8, 2026
San Francisco Public Utilities Commission

The SFPUC approved Amendment No. 2 to increase the contract amount by $2,000,000, bringing the total to $30,780,000, with no change to the contract duration.

PUC Reso No. 26-0150 090826
6
Received from DepartmentSeptember 28, 2026
Clerk of the Board

The Clerk received the proposed resolution for Amendment No. 2 from the SFPUC.

Leg Ver1
7
Pending Committee ActionPending
San Francisco Board of Supervisors

The resolution for Amendment No. 2 is currently pending committee action.

Leg Ver1

Reconstructed from attached documents & the official record

Related / predecessor legislation
โ†‘ predecessor#151169โ€” not yet in database
โ†‘ predecessor#220413โ€” not yet in database
Document trail
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—
BLA Rpt 102826
Budget and Legislative Analyst
PDF โ†—
PDF โ†—
PDF โ†—
PDF โ†—

How they voted

Legislative journey

Clerk of the BoardSep 28, 2026
ยทRECEIVED FROM DEPARTMENT
PresidentOct 6, 2026
โ†’RECEIVED AND ASSIGNED
Budget and Finance CommitteeOct 28, 2026
โœ“RECOMMENDEDPass
Board of SupervisorsNov 3, 2026
โœ“ADOPTEDPass